Question

Accounting

A business is launching a new product. The launch will require a number of related activities as follows - Hire the Project Manager - [6 weeks] , Hire Salesmen - [6 weeks], Train Salesmen - [10 weeks], Select Advertising Agency - [2 weeks] , Plan Advertising Campaign - [4 weeks] , Conduct Advertising Campaign - [10 weeks] , Design Package - [11 weeks] ,Set-up Packaging Facilities - [10 weeks], Package initial stocks - [6 weeks] , Order stock from Manufacturer - [13 weeks] , Select Distributors - [9 weeks] , Sell to the Distributors - [4 weeks] , Ship stock to Distributors - [10 weeks] .

a. Determine and label the critical path clearly on the network diagram, using the stages (A-B-C-D) etc?

b. What is the earliest number of weeks in which we can plan the ad campaign?

c. If Order stock from the Manufacturer was delayed 9 weeks, what would happen to the project's duration?

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students