8. if the project duration needs to be reduced then a. the activity with the lost...

80.2K

Verified Solution

Question

General Management

8. if the project duration needs to be reduced then

a. the activity with the lost cost should be selected

b. activity which is currently undergoing should be selected

c. activity with the highest cost should be selected

d. activity on the critical path should be selected

.

9. it does not make any sense to crash if

a. if there is no critical activity left

b. project crashing cost is equal or more than saving

c. project is more than 75% compelet

d. project crashing cost can not be calculated

.

10. forecast errors can not be attributed to

a. sudden change in trend

b. past sales data

c. random variation

d. change in business environment

Answer & Explanation Solved by verified expert
4.0 Ratings (511 Votes)
Answer to question 8 A project has multiple sets of paths consisting of various activities Out of these paths one or more than one isare critical paths Critical paths are those which takes maximum time to execute and complete Naturally Project duration becomes equivalent to the duration of the critical path All other noncritical paths will have    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students