All cash flows from a project are shown in the diagram below.
Which formula calculates the correct internal rate of return for the project?
\table[[4,A,B,C,D,],[1,,The valuation date is December 1,2024.],[2,],[3,,(YY-MM-DD),Cashflows,,],[4,,,],[5,,12-31-2023,(150,000),,],[6,,12-01-2024,(100,000),,],[7,,12-12-2025,84,000,,],[8,,12-04-2026,90,000,,],[9,,12-07-2027,98,000,,],[10,,12-08-2028,120,000,,]]
?x=I RR(C6:C10,B6:B10)
?x=I RR(C5:C10,B5:B10)
=IRR(C5:C10)
?x=I RR(B5:B10,C5:C10)
image

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Zin AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students