/63397/history?version-4 Question 10 10/10 pts A project manager has collated the following information about one...
70.2K
Verified Solution
Question
Accounting
/63397/history?version-4 Question 10 10/10 pts A project manager has collated the following information about one of their ongoing projects. Task Name Duration Start Date End Date Labour Materials % % Actually Actual Planned complete Cost compete Initiation 5 days Wed Tue $2,500 $250 100% 100% $2,900 29/09/21 5/10/21 Planning 10 days Tue 5/10/21 Tue $4,000 $50 100% 100% $3.900 19/10/21 Phase 1 15 days Tue Mon $9,000 $600 100% 100% $9.900 19/10/21 8/11/21 Phase 2 10 days Mon Fri $6,000 $400 100% 9096 $6,100 8/11/21 19/11/21 Phase 3 5 days Fri 19/11/21 Fri $5,000 $200 60% 40% $1.500 26/11/21 Modifications 12 days Mon Tue $7,200 $160 30% 2096 $600 8/11/21 23/11/21 Integration Fri 26/11/21 Thu $2,500 $1,400 0% 096 $ 2/12/21 Final Test 4 days Fri 3/12/21 Wed $2.000 $500 096 0% $0 8/12/21 Client 1 day Wed Thu $1,500 $100 09 $0 Handover 8/12/21 9/12/21 Using the following assumptions: . Both Indirect costs and contingency costs are both estimated at 10% of all direct costs All variations are of the common cause" type Calculate the Estimate At Completion and the updated Project Cost Estimate. The Estimate At Completion is $41.991 5 days % 50 0% The Project Cost Estimate is $50,389 /63397/history?version-4 Question 10 10/10 pts A project manager has collated the following information about one of their ongoing projects. Task Name Duration Start Date End Date Labour Materials % % Actually Actual Planned complete Cost compete Initiation 5 days Wed Tue $2,500 $250 100% 100% $2,900 29/09/21 5/10/21 Planning 10 days Tue 5/10/21 Tue $4,000 $50 100% 100% $3.900 19/10/21 Phase 1 15 days Tue Mon $9,000 $600 100% 100% $9.900 19/10/21 8/11/21 Phase 2 10 days Mon Fri $6,000 $400 100% 9096 $6,100 8/11/21 19/11/21 Phase 3 5 days Fri 19/11/21 Fri $5,000 $200 60% 40% $1.500 26/11/21 Modifications 12 days Mon Tue $7,200 $160 30% 2096 $600 8/11/21 23/11/21 Integration Fri 26/11/21 Thu $2,500 $1,400 0% 096 $ 2/12/21 Final Test 4 days Fri 3/12/21 Wed $2.000 $500 096 0% $0 8/12/21 Client 1 day Wed Thu $1,500 $100 09 $0 Handover 8/12/21 9/12/21 Using the following assumptions: . Both Indirect costs and contingency costs are both estimated at 10% of all direct costs All variations are of the common cause" type Calculate the Estimate At Completion and the updated Project Cost Estimate. The Estimate At Completion is $41.991 5 days % 50 0% The Project Cost Estimate is $50,389

Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.