4.) You are managing a task on the critical path which has a BAC of $500,000....

50.1K

Verified Solution

Question

Operations Management

4.) You are managing a task on the critical path which has a BACof $500,000. The task is 80 percent complete. The team hascompleted 10 weeks on the task, and it was scheduled to take 10weeks. You have spent $400,000 on the task so far. Calculate thecost performance index (CPI) and schedule performance index (SPI).Briefly explain what the reults mean.

Answer & Explanation Solved by verified expert
3.7 Ratings (608 Votes)
Total end value 500000 Since 80 of the project is over Earned Value 8 500000 400000 Actual cost 400000 Cost Performance Index CPI Earned Value Actual Cost 400000 400000 100 Hence the project is in    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students