4. What is the total project budget in this time-phased budget? Activity July August September October November RFP 31,000 Analysis 3,000 15,000 Design 23.000 34.000 Coding 46,000 Testing 10,000 Training 15,000 15,000 Roll-Out 18,000 A) $210,000 B) $193,000 C) $184,500 D) $178,300