3a. Explain to the Contractor the content requirements of the programme under the NEC4 ECC Option...

50.1K

Verified Solution

Question

General Management

3a. Explain to the Contractor the content requirements of theprogramme under the NEC4 ECC Option B and the consequences of notmeeting them.

3b.By reference to Clauses in the contract mentioning theContractor’s programme, outline its contractual significance.

Answer & Explanation Solved by verified expert
3.9 Ratings (592 Votes)
Content requirements of the programme under NEC4 ECC Option B It is used for the appointment of a contractor for engineering and construction work including any level of design responsibility Under Option B the bill of quantities is a traditional bill of quantities ie a document prepared by the cost consultant often a quantity surveyor that provides project specific measured quantities of the items of work identified by    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students