37.Job A-15 was recently completed. The job cost sheet shows $1,200 of direct materials and...
60.1K
Verified Solution
Question
Accounting
37.Job A-15 was recently completed. The job cost sheet shows $1,200 of direct materials and direct labor wages of $500. The companys direct labor wage rate is $20 per hour and it applies overhead at a rate of $12 per direct labor hour. How much overhead would be applied to job A-15?
A. $720
B. $1,020
C. $240
D. $300
38.Job 123 used $50,000 in direct materials and direct labor wages were $40,000. Manufacturing overhead of $80,000 was applied to the job. The predetermined overhead rate used to apply overhead was $15 per machine hour. Actual manufacturing overhead cost incurred amounted to $76,000. Based on this information, what is the total cost of Job 123? A. $170,000 B. $90,000 C. $166,000 D. $246,000
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.