3. Which of the following best describes the relationship between IRR and NPV rules? If...

50.1K

Verified Solution

Question

Accounting

3. Which of the following best describes the relationship between IRR and NPV rules?

If IRR of project A is greater than IRR of project B, accept A even if NPV of B is higher

If NPV of project B is greater than NPV of project A, accept B even if IRR of A is higher

If IRR of project A is lower than hurdle rate and IRR of B is higher than hurdle rate, accept project A because it will have a higher NPV

If NPV of project A is higher than B and IRR of project B is higher than project A, decide with payback rule

If IRR of project B is equal to the discount rate and NPV of B is positive, accept project B.

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students