3. The client of a project has requested the project team to crash 8 hours of...

60.1K

Verified Solution

Question

General Management

3. The client of a project has requested the project team tocrash 8 hours of time. The table below provides the necessaryinformation about the possible project crashing.

(a) What is the crash cost for 8 hours of time-savings?

(b) Assume the team calls the client and asks for a projectextension, reducing the amount of time they need to crash. Theproject team has a $20 crash budget. Is the budget sufficient tocrash 4 hours of time?

Activity

Normal

Duration (hours)

Normal

Cost ($)

Crash

Duration (hours)

Crash

Cost (S)

Immediate

Predecessors

A

2

10

2

0

None

B

3

15

2

23

A

C

5

25

4

30

B

D

3

20

1

24

C

E

6

30

4

45

C

F

1

5

1

0

C,E

G

7

35

6

50

F

H

10

50

7

62

D,G

Evaluation

The Unit Exercises will be marked in its entirety out of 100.The following rubric indicates the criteria students are to adhereto, and their relative weights to the assignment overall.

Answer & Explanation Solved by verified expert
4.3 Ratings (1083 Votes)
PLEASE LIKE THIS ANSWER ITHELPS ME A LOT THANK YOUSolutionNetwork DiagramPossible PathsStartABCDHEnd 23 hoursStartABCEFGHEnd 34 hours CriticalPath longest duration pathStartABCFGHEnd 28    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students