3. Smith’s bid of $542,000 was the lowest on a construction project that was advertised. The...

70.2K

Verified Solution

Question

Civil Engineering

3. Smith’s bid of $542,000 was the lowest on a constructionproject that was advertised. The cost of the largest constructioncontract which Smith had previously performed was $78,000. Whatshould the owner do to determine whether or not to let the contractto Smith?