3. Given the project network and baseline information below, complete the form to...

70.2K

Verified Solution

Question

Accounting

3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what information are you prepared to tell the customer about the status of the project at the end of period 8?
image
image
t luf project managers to resist changes to the project baseline Under what conditions would a project manager make changes to a would a project manager not allow changes to a baseline? 1. In month 9 the following project information is available: actual cost is $2.000 earned value is $2,100, and planned cost is $2,400. Compute the SV and CV for the project. 2. On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51? 3. Given the project network and baseline information below, complete the form to develop a status report for the project at the end of period 4 and the end of period 8. From the data you have collected and computed for periods 4 and 8, what informa- tion are you prepared to tell the customer about the status of the project at the end of period 8? LEGEND ES ID EF SL LS DUR LF 81D112 8 4 12 2 6 8 12 F 15 12 3 15 9 3 12 4 5 9

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students