1a) Explain the procedure for dealing with a compensation event under the NEC4 ECC, Option B. 1b)...

60.1K

Verified Solution

Question

General Management

1a) Explain the procedure for dealing with a compensation eventunder the NEC4 ECC, Option B.

1b) A Contractor is engaged under a contract incorporating NEC4ECC Option B. All of the design of the works has been provided bythe Client’s consultants. The works require 3000 cubic metres ofconcrete. The Contractor has noticed the following problem: whilstit is stated in the drawings in the Scope that the concrete must beGrade C30, it is stated in the specification section of the Scopethat the concrete is to be Grade C40. The unit cost of Grade C30 is£70 per cubic metre whilst that of Grade C40 is £80 per cubicmetre.Assuming that the drawings are wrong, advise the Contractorand the Project Manager on the actions to be taken.

Answer & Explanation Solved by verified expert
4.3 Ratings (854 Votes)
Under the NEC4 forms compensation events are events which are not the fault of the contractor or subcontractor The contractor has to notify a compensation event within eight weeks Under NEC Contract if any fault or failure happened it is highly recommended to resolve by a mutual trust and cooperation The contractors right is to complete the event effectively as planned and shown on the accepted programme Compensation Event procedure If a compensation event which arises from    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students