1-A building requires a 100-foot long by 83-foot wide by 5-inch thick concrete slab. Using a...

60.1K

Verified Solution

Question

Civil Engineering

1-A building requires a 100-foot long by 83-foot wide by 5-inchthick concrete slab. Using a waste factor of 10 %, Includecalculations. a)determine the number of cubic yards of concreteneeded to pour the slab. (2 points)

2-Determine the number of rolls of wire mesh needed if there are750 SF of wire per roll and 12% of waste. Include calculations. (2points) 9 BCT 2770 Estimating Fundamentals

3-Determine the amount of rebar needed for the slab if it isreinforced with #4 rebar at 12 inches on center both ways. Assume 2inches of cover and add 10% for lap and waste. Includecalculations.(11 points) Tip=Use the density method

4-Determine the cost to finish the slab using a productivity of0.011 labor hours per SF and an average labor rate of $29.92 perlabor hour. Include calculations.(2 points)

5-A vapor barrier is to be placed below the slab. Determine thenumber of 10-foot by 100-foot rolls of vapor barrier needed. Thevapor barrier needs to be lapped one foot. Hint: Subtract the lapfrom the width of the roll. Include calculations. (2 points)

Answer & Explanation Solved by verified expert
4.4 Ratings (824 Votes)
Ans 1 Required volume V L x B x H V 100 ft x 83 ft x 5 in12 inft V 345833 Since 10 contribute to waste actual volume required 1 01 x 345833 380416 1 cubic yard 27 Required volume 380416    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students