13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX...

50.1K

Verified Solution

Question

Advance Math

13.7 Table EX 13.7 shows the precedencerelationships among the activities to complete a project.

Table EX 13.7

Activity

Predecessor

Duration (Weeks)

A

6

B

2

C

A

4

D

B

5

E

B

2

F

C, D

4

G

C, D

7

H

E, G

5

I

F

4

  1. Construct an activity on node network for the project.
  2. Identify the paths and path project durations.
  3. Determine the critical path and the expected project completiontime.
  4. Find the ES, LS, EF, LF, and slack time for each activity.

Answer & Explanation Solved by verified expert
3.7 Ratings (660 Votes)
Construct an activity on node network for theprojectIdentify the paths and path projectdurationsPathDurationWeeksACGH6475 22ACFI6444 18BDFI2544 15BEH225 9BDGH2575 19Determine the critical path and the expected projectcompletion timeCritical path is the longest path and here the critical path isACGH with duration 22 weeksExpected project completion time is duration of critical path 22 weeksFind the ES LS EF LF and slack time for    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students