11-40 Make or buy, unknown level of volume. (A. Atkinson, adapted) Denver Engineering...
90.2K
Verified Solution
Question
Accounting
11-40
Make or buy, unknown level of volume. (A. Atkinson, adapted) Denver Engineering manufactures small engines that it sells to manufacturers who install them in products such as lawn mowers. The company currently manufactures all the parts used in these engines but is considering a proposal from an external supplier who wishes to supply the starter assemblies used in these engines.
The starter assemblies are currently manufactured in Division 3 of Denver Engineering. The costs relating to the starter assemblies for the past 12 months were as follows: Direct materials $ 400,000 Variable direct manufacturing labor 300,000 Manufacturing overhead 800,000 Total $1,500,000 Over the past year, Division 3 manufactured 150,000 starter assemblies. The average cost for each starter assembly is $10 ($1,500,000150,000).$10 ($1,500,000150,000).
Further analysis of manufacturing overhead revealed the following information. Of the total manufacturing overhead, only 25% is considered variable. Of the fixed portion, $300,000 is an allocation of general overhead that will remain unchanged for the company as a whole if production of the starter assemblies is discontinued. A further $200,000 of the fixed overhead is avoidable if production of the starter assemblies is discontinued. The balance of the current fixed overhead, $100,000, is the division manager's salary. If Denver Engineering discontinues production of the starter assemblies, the manager of Division 3 will be transferred to Division 2 at the same salary. This move will allow the company to save the $80,000 salary that would otherwise be paid to attract an outsider to this position.
Required
- Tutwiler Electronics, a reliable supplier, has offered to supply starter-assembly units at $8 per unit. Because this price is less than the current average cost of $10 per unit, the vice president of manufacturing is eager to accept this offer. On the basis of financial considerations alone, should Denver Engineering accept the outside offer? Show your calculations. (Hint: Production output in the coming year may be different from production output in the past year.)
- How, if at all, would your response to requirement 1 change if the company could use the vacated plant space for storage and, in so doing, avoid $100,000 of outside storage charges currently incurred? Why is this information relevant or irrelevant?
Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.