10-Data analysis is a technique used in control scope process; variance analysis and data analysis are...

90.2K

Verified Solution

Question

General Management

10-Data analysis is a technique used in control scopeprocess; variance analysis and data analysis are two differenttechniques of data analysis, which answer? describes varianceanalysis and trend analysis correctly

A- Variance analysis examines project performance over time todetermine if progress is deteriorating or improving, while trendanalysis compares baseline to actual results and determines ifpreventive actions or corrective actions are required

B- Trend analysis examines project performance over time todetermine if progress is deteriorating or improving, while varianceanalysis compares baseline to actual results and determines ifpreventive actions or corrective actions are required

C- Trend analysis categorize requirements, while varianceanalysis decomposes project scope into more manageablecomponents

D- Variance analysis categorize requirements, while trendanalysis decomposes project scope into more manageablecomponents

11- Which of the following are theoutputs of collect requirements process

A- Scope management plan. and requirements management plan

B- Requirements documentation, and requirements traceabilitymatrix

C- Scope baseline, and project documents update

D- WBS and WBS dictionary

12-How to measure the completion of the product scopeand the project scope?

A- The completion of the product scope is measured against thescope management plan, while the completion of project scope ismeasured against the requirements documentation

B- The completion of the product scope is measured against thescope management plan, while the completion of project scope ismeasured against the requirements traceability matrix

C- The completion of the product scope is measured against theproject management plan, while the completion of project scope ismeasured against the requirements documentation

D- The completion of the product scope is measured against theproduct requirements, while the completion of project scope ismeasured against the project management plan

Answer & Explanation Solved by verified expert
4.0 Ratings (519 Votes)
Answer 1 B Trend analysis is defined as the analysis that examines the performance of the project over time to determine if its deteriorating or improving It helps in forecasting future performance based on past results Variance analysis is defined as the analysis that determines the cause    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students