1) What is an important aspect of ethics that will keep you out of “The Gray...

70.2K

Verified Solution

Question

Civil Engineering

1) What is an important aspect of ethics that will keep you outof “The Gray Zone”?

Question 1 options:

A) Knowing right from wrong

B) Perception of others

C) Do the right thing even when no one else is looking

D) Don’t worry about it, society is binary when it comes toethics

Question 2 (5 points)

2) Who are project stakeholders?

Question 2 options:

A) Owner, Prime contractor, subcontractors

B) Engineer, Architect, Vendor

C) A group who may affect the project and be affected by theproject

D) Customers, surrounding community, press (reporters)

E) All of the above

Question 3 (5 points)

3) OSHA stands for______?

Question 3 options:

A) Occupational Safety in Human Affairs

B) Occupational Standards in Health Act

C) Occupational Safety and Health Administration

D) A whale that performs at Sea World in San Diego

E) I don’t know and I don’t care

Question 4 (5 points)

4) Which of the following would NOT beconsidered a Direct Cost?

Question 4 options:

A) Material

B) Equipment

C) Project Overhead

D) Labor

Question 5 (5 points)

5) Which form of company ownership includes two or more ownerswhose personal assets are at risk?

Question 5 options:

A) Sole Proprietor

B) Partnership

C) Limited Liability Company

D) Corporation

Question 6 (5 points)

6) Which one is not considered a form of ADR?

Question 6 options:

A) Mini Trial

B) Dispute Review Board

C) Arbitration

D) Mediation

E) Negotiations

Question 7 (5 points)

7) Arbitration is Legally binding and is typically included withthe contract documents?

Question 7 options:

True
False

Question 8 (5 points)

8) What is considered the stage in the progress of the Work whenthe Work or designated portion thereof is sufficiently complete inaccordance with the Contract Documents so that the Owner can occupyor utilize the Work for its intended use

Question 8 options:

A) Final Completion

B) Substantial Completion

C) Significant Completion

D) Commissioning Deadline

Question 9 (5 points)

9) What are the primary purposes of OSHA?

Question 9 options:

A) Set & enforce safety standards

B) Train and educate

C) Provide assistance and outreach

D) All of the Above

Question 10 (5 points)

10) The ________ the Experience Modification Rate (EMR) of yourbusiness, the ________ your worker compensation insurance premiumswill be.

Question 10 options:

A) Lower, higher

B) Lower, lower

C) Higher, Lower

D) Higher, higher

Question 11 (5 points)

11) What might contingency be used for?

Question 11 options:

A) To cover unforeseen costs

B) To manage a job's budget

C) To hold an owner liable

D) To perform a quantity takeoff

Question 12 (5 points)

12) Which of the following reason for defects can a Contractortrypically not Control?

Question 12 options:

A) Faulty Design

B) Faulty Workmanship

C) Faulty materials

D) All of the above

Question 13 (5 points)

13) What type of contract does the owner controlcontingency?

Question 13 options:

A) Guaranteed max Price

B) Lump Sum

C) Design Build

D) Design Bid Build

Question 14 (5 points)

14) What is construction quality?

Question 14 options:

A) Meeting the specifications in the contract documents

B) Meeting the needs and expectations of the owner

C) Ensure facilities perform to its intended purpose

D) Avoid dispute claims

E) All of the above

Question 15 (5 points)

15) Which form of dispute resolutions does not allow an appealprocess?

Question 15 options:

A) Litigation

B) Mediation

C) Communication

D) Arbitration

Question 16 (5 points)

16) What is included in a Gannt Chart?

Question 16 options:

A) Permitting and long lead items

B) Critical Path

C) Must show work being completed within contractualtimeline

D) Float

E) All of the above

Question 17 (5 points)

17) Right-to-work state prohibit unions from organizing?

Question 17 options:

True
False

Question 18 (5 points)

18) Which of the following is considered a soft skill?

Question 18 options:

A) Reading Blueprints

B) Building a schedule

C) Communicating with people

D) Performing quality control

E) All of the above

Question 19 (5 points)

19) Who is a safety officer on a project site?

Question 19 options:

A) The project safety officer

B) Superintendent

C) Project Engineer

D) Everyone on the project site

E) Foreman

F) None of the above

Question 20 (5 points)

20) What plan is not part of the key elements for SiteLogistics?

Question 20 options:

A) Job site layout plan

B) Site Utlitiy plan

C) Emergency Action plan

D) Schedule contingecy plan

E) Storm water pollution plan

F) Hoisting plan

Question 21 (5 points)

21) Labor unions use collective bargaining for what?

Question 21 options:

A) Wages

B) Benefits

C) Working Conditions

D) Lobbying

E) All of the Above

Question 22 (5 points)

22) Do Heavy Civil contract documents typically use the CSIdivision format?

Question 22 options:

Yes

No

Answer & Explanation Solved by verified expert
3.6 Ratings (512 Votes)
1 What is an important aspect of ethics that will keep you out of The Gray Zone Answer C Do the right thing even when no one else is looking Question 2 5 points 2 Who are project stakeholders Answer C A group who may affect the project and be affected by project Question 3 5 points 3 OSHA stands for C Occupational Safety and Health Administration Question 4 5 points 4 Which of the following would NOT be considered a Direct Cost Answer C    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students