1. To minimize the chance of losses, what process should a contractor use for updating the...

90.2K

Verified Solution

Question

Civil Engineering

1. To minimize the chance of losses, what process should acontractor use for updating the schedule, if litigation isexpected?

2. Explain how prefabrication can change the critical path of aschedule.

3. For the ISU Chiller Plant, how did craft workers lift heavyitems inside the plant?

Answer & Explanation Solved by verified expert
4.2 Ratings (800 Votes)
Answer 1 Contractors often use completion date bar chart and percentage of completion schedules to track progress coordinate subcontractors and monitor delays but the law may require more sophisticated scheduling methods such as Critical Path Method Program Evaluation and Review Technique or Precedent Diagramming Method as a part of the contractors obligations in case of litigation For example the contractor can add the amount of hours actually worked on a task to    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students