1. the following information is provided for an intersection that will have signalization. calculate the signal...

70.2K

Verified Solution

Question

Civil Engineering

1. the following information is provided for an intersectionthat will have signalization. calculate the signal timing for a twophase system also show the phase diagram .

peak hour volumes: SB/NB/WB/EB;360/300/444/482 vph

PHP; SB/NB/WB/EB:0.92/0.88/0.90/0.82

saturation flow: SB/NB/WB/EB:1500/1500/1800/1800vph

distribution of vehicles for turning movements

South bondNorth bondWest bondEast bond
TMT R L   T R LT R L   T R L   
% of TM90 4 6   88 7 5   84 8 686 15 1
% of CV3 0 3   4 14 42 8 104 15 7

yellow interval 3.1 sec. for SB-NB, and 3.4 sec. for WB-EB; losttime 3.3 sec for each of the phases.

2. its a question from transportation

Answer & Explanation Solved by verified expert
4.0 Ratings (463 Votes)
We are told to assume its a two phase Signal so we haveApproachPhase 1SBNBPhase 2WBEBThe phase diagram is shown asDHV givent turn flowphf so for NB it wil be 30088 341Now in SB approach 391 is DHB and are given 90 is throughvolume and 4    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students