1. on February 1, 2019, Strawser Construction agreed to construct a building at a contract...
90.2K
Verified Solution
Question
Accounting
1. on February 1, 2019, Strawser Construction agreed to construct a building at a contract price of $4,500,000 Strawser estimated total construction costs would be $4.000.000 and the project would be finished in 2021 Information relating to the costs and billings for this contract is as follows: Total costs incurred to date 2019 2020 2021 Estimated costs to complete $1,500,000 $2,460,000 $4,200,000 2,500,000 1.640.000 Customer billings to date 2,200,000 4,000,000 Collections to date 4,500,000 2,000,000 3,500,000 4.500.000 Instructions a. Fill in the correct amounts on the following schedule. For over time percentage of completion) accounting show the gross profit that should be recorded for 2019, 2020, and 2021 Gross Profit 2019 2020 2021 repare the journal entries necessary for 2021 using over time (percentage of completion) Accounting (use the back if necessary)

Get Answers to Unlimited Questions
Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!
Membership Benefits:
- Unlimited Question Access with detailed Answers
- Zin AI - 3 Million Words
- 10 Dall-E 3 Images
- 20 Plot Generations
- Conversation with Dialogue Memory
- No Ads, Ever!
- Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Other questions asked by students
StudyZin's Question Purchase
1 Answer
$0.99
(Save $1 )
One time Pay
- No Ads
- Answer to 1 Question
- Get free Zin AI - 50 Thousand Words per Month
Best
Unlimited
$4.99*
(Save $5 )
Billed Monthly
- No Ads
- Answers to Unlimited Questions
- Get free Zin AI - 3 Million Words per Month
*First month only
Free
$0
- Get this answer for free!
- Sign up now to unlock the answer instantly
You can see the logs in the Dashboard.