1. Develop an estimated duration for each activity. ...

90.2K

Verified Solution

Question

Accounting

1. Develop an estimated duration for each activity.
Below is a table showing the activities that will take place at a wedding and the estimated time for each activity.
Activity Estimated time(days)
Setting up a date 4
Coming up with the budget 20
Identifying the guests 14
Selecting the vendors and the caterers 28
Setting up the themes 10
Deciding on the cake 5
Getting the best man and the bridesmaid and their dresses 21
Wedding dress 14
Honeymoon reservations 5
Enrolling for dance classes 21
Confirming the head count 5
Preparing for the big day 5
Activity Estimated time(days) Early start time(days) Late start time(days) Early finish time(days) Late finish time(days)
Setting up a date 4 0 0 4 4
Coming up with the budget 20 5 5 25 25
Identifying the guests 14 26 26 40 40
Selecting the vendors and the caterers 28 41 41 69 69
Setting up the themes 10 42 70 52 80
Deciding on the cake 5 81 81 86 86
Getting the best man and the bridesmaid and their dresses 21 82 87 103 108
Wedding dress 14 109 109 123 123
Honeymoon reservations 5 124 124 129 129
Enrolling for dance classes 21 130 130 151 151
Confirming the head count 5 152 152 157 157

Preparing for the big day

This is my Q d. Produce a bar chart (Gantt Chart) based on the ES and EF times from the schedule in item 2.

5 158 158 163 163

Answer & Explanation Solved by verified expert
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students