1) Consider the network corresponding to the following information. Activity Immediate Predecessor(s) Time (Weeks) A --- 3 B --- 4 C A 6 D B 9 E B 6 F C, D 6 G D, E 8 H G, F 9 Draw the network corresponding to...

90.2K

Verified Solution

Question

General Management

1) Consider the network corresponding to the followinginformation.

Activity

Immediate

Predecessor(s)

Time

(Weeks)

A

---

3

B

---

4

C

A

6

D

B

9

E

B

6

F

C, D

6

G

D, E

8

H

G, F

9

  1. Draw the network corresponding to the aboveinformation.
  2. Using a table format, identify the criticalpath.
  3. What is the project completion time?

Answer & Explanation Solved by verified expert
4.0 Ratings (620 Votes)
2 Criticalpath It is the longestdistance between the start and finish of the projectTheavailable paths areACFH 24BDFH 28BDGH 30BEGH 27Herethe critical path is BDGH as it has longest timedurationHenceES and EF are    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students