1. Agile Methods Practice Problems. Complete these problems, showing your work. 1a. At the end of Day 1...

80.2K

Verified Solution

Question

Basic Math

1.Agile Methods Practice Problems. Complete these problems, showingyour work.

1a. At the end of Day 1 of asprint there are 90 story points worth of work remaining, and atthe end of Day 6 there are 40 story points of work remaining. Whatis the project’s current velocity, in units of story points perday? (Show your work)

1b. A project whose sprintvelocity is 12 story points per day at the end of Day 4, and with132 story points remaining will finish at the end of what day?(Show your work)

Answer & Explanation Solved by verified expert
4.3 Ratings (995 Votes)
Let T represent the total story points of work to be completedin the projectX represent the projects current velocityin units of storypoints per    See Answer
Get Answers to Unlimited Questions

Join us to gain access to millions of questions and expert answers. Enjoy exclusive benefits tailored just for you!

Membership Benefits:
  • Unlimited Question Access with detailed Answers
  • Zin AI - 3 Million Words
  • 10 Dall-E 3 Images
  • 20 Plot Generations
  • Conversation with Dialogue Memory
  • No Ads, Ever!
  • Access to Our Best AI Platform: Flex AI - Your personal assistant for all your inquiries!
Become a Member

Other questions asked by students