1 A loader has a full bucket capacity of 10 yd3 and the average time...

80.2K

Verified Solution

Question

Basic Math

image

1 A loader has a full bucket capacity of 10 yd3 and the average time required to place one bucketload of soil into a truck is 1 min The loader is supported by four trucks with a volume of 50 yd3 each and a cycle time of 12 min plus the time to load the truck The ideal productivity yd3 hr of this system is most nearly

Answer & Explanation Solved by verified expert